Wednesday, 14 April 2021

Injunction on Invocation of Bank Guarantees on Ground of Egregious Fraud

 

When there is default in performance of contract and an unconditional bank guarantee is furnished, Courts generally do not interfere in its invocation even though the dispute is still pending between beneficiary and person on whose behalf guarantee is given.  However there are exceptions to this rule. Situation of egregious fraud - Fraud committed of a nature that would vitiate the entire underlying transaction[1].

Facts[2]

A petition was filed by appellant under Sec 9 of Arbitration and Conciliation Act, 1996 seeking orders restraining the Respondent from encashing bank guarantees. The Ld Single Judge in fact directed encashing the four bank guarantees and transfer the encashed amount into the account of the learned Registrar General of this Court, to be put in a fixed deposit subject to the outcome of the arbitration proceedings. An appeal was preferred against this order

The case of appellant in brief is that it was assigned contract for extraction of coal from an ascertained coal block. The (Detailed Project Report) DPR for the same was cleared by Respondent. Consequent to this unconditional bank guarantees were furnished by appellant.

After sometime it was found upon examination of coal block (by Respondent) that the amount of coal extraction is likely to be greatly reduced. This was informed to appellant. This variation was, according to appellant, were at great variance to the earlier Geological Reports and called for entire fresh planning of work execution; its associated cost changes/variations; approval of a fresh mining plan; obtaining fresh environmental clearance; change in locations of ventilation shaft and inclined drivages and other key issues.

The issues were communicated to Respondent which decided to form a Committee to look into issues. However even after 12 months to communication was made to appellant and abruptly a shoe cause notice was issued by Respondent for cancellation of contract.

Even though appellant tried its best that respondent withdraws the cancellation notice but instead a letter communicating cancellation of contract was issued. The appellant filed the above Sec 9 petition seeking interim measures for protection against which an appeal was filed.

Ratio

It was noted that bank guarantees furnished by appellant are unconditional in nature meaning thereby “the bank has undertaken to pay to the beneficiary immediately on demand all monies payable by the contractor to the extent of the amounts specified therein, without any demur, reservation, recourse, contest or protest and/or without any reference to the appellant contractor”. Terms and Conditions stipulated in the contract give an absolute right to Respondent to encash the bank guarantees in accordance with the terms captured above.

Appellant raises the ground of egregious fraud by Respondent to obtain injunction against encashment of bank guarantee. But the Court states that – “the Appellant’s contention is vague and does not meet the requirement of law on the concept of fraud as a ground for restraining encashment of bank guarantees, as laid down in a plethora of judgments on the subject”

Further the appelants’s prayer that Contract be declared void ab intio also was not accepted by the court on a simple reason that arbitration proceedings are pending and it was beyond the scope of Sec 9 petition under the Act to grant such a relief.

The encashment of bank guarantee cannot be termed as fraudulent only because disputes arose between parties even if it was accepted that Respondent was at fault for failing to fulfill its obligations under the Contract. – “The existence of disputes between the parties to the Contract is not a ground for issuing an order of injunction to restrain enforcement of bank guarantees.”

Also the Ld single judge has not assigned the amount to Respondent rather has been deposited in the Court subject to outcome of arbitration proceedings.

Thus the plea of appellant was not accepted.



[1]  U.P. State Sugar corporation v Sumac International Ltd (1997) 1 SCC 568

[2] AMR BBB Consortium v Bharat Cooking Coal Ltd (Delhi High Court, FAO(OS) (COMM) 20/2021)

No comments:

Post a Comment